Power & Electrical

Toshiba Transformer Handling — Kolkata

Precision handling and positioning of a Toshiba power transformer at a Kolkata substation project.

Toshiba
Kolkata, West Bengal
Completed in 1 day
Toshiba Transformer Handling — Kolkata
Toshiba OEM handling compliance
Tilt and shock monitoring throughout
Single-lift precision placement
Zero handling exceedances

The Challenge

The Toshiba transformer required careful handling due to strict OEM specifications on tilt angles and shock limits during unloading and placement.

Our Approach

The lift plan was prepared as per Toshiba's handling manual. Tilt indicators were monitored throughout the lift. The crane operator executed a controlled single-lift placement with constant communication from ground spotters.

The Result

Transformer placed within OEM-specified tolerances. Toshiba's site engineer confirmed no tilt or shock limit exceedances during the operation.

Project Details

Client
Toshiba
Sector
Power & Electrical
Location
Kolkata, West Bengal
Duration
1 day

Equipment Used

  • Hydraulic Crane
  • Rollers
  • Slings