Power & Electrical

510 MVA Transformer Unloading & Foundation Shifting

Unloading and precision shifting of a 510 MVA power transformer to its foundation pad at Satgachi sub-station, Bardwan. One of the heaviest single-piece lifts handled by IPN Lifters.

Larsen & Toubro
Bardwan, West Bengal
Completed in 3 days
510 MVA Transformer Unloading & Foundation Shifting
510 MVA — one of the heaviest transformer lifts in Eastern India
Shifted 40m through live electrical bays
Completed within planned shutdown window
Zero-incident operation with L&T

The Challenge

The 510 MVA transformer — one of the largest capacity units in the eastern grid — had to be unloaded from a multi-axle trailer and shifted to the foundation inside the sub-station compound. The foundation pad was positioned 40 metres from the unloading point with a narrow corridor between existing live electrical bays.

Our Approach

A detailed method statement was prepared in coordination with L&T's project team. The transformer was unloaded using a 100T hydraulic crane onto a roller track system. Hydraulic jacks and pipe rollers were used to inch the unit along the pre-surveyed route, maintaining clearance from live equipment at all times. The entire operation was supervised with real-time load monitoring.

The Result

The 510 MVA transformer was successfully positioned on its foundation with millimetre-level accuracy. Zero incidents recorded, and the operation was completed within the planned shutdown window.

Project Details

Client
Larsen & Toubro
Sector
Power & Electrical
Location
Bardwan, West Bengal
Duration
3 days

Equipment Used

  • Hydraulic Crane 100T
  • Hydraulic Jacks
  • Pipe Rollers
  • Wire Rope Slings

Similar Project?

Get a Quote for Your Site

Request a QuoteTalk to Our Team

Project Photos

510 MVA Transformer Unloading & Foundation Shifting — Photo 1
510 MVA Transformer Unloading & Foundation Shifting — Photo 2
510 MVA Transformer Unloading & Foundation Shifting — Photo 3