Chiller Installation — Ozone Project, Patna
Unloading and installation of chiller equipment at the Ozone commercial project in Patna, Bihar.
Ozone Group
Patna, Bihar
Completed in 1 day

Active construction site coordination
Multi-contractor environment managed
Single-lift installation
On-schedule delivery in Patna
The Challenge
The commercial project site in Patna had ongoing construction activities with multiple contractors working simultaneously. Coordinating the chiller lift with other construction operations required careful scheduling.
Our Approach
Close coordination with the Ozone project management team ensured a clear work window for the chiller installation. The crane was positioned to avoid conflict with other construction activities, and the chiller was placed on its foundation in a single, planned lift.
The Result
Chiller installed on schedule without disrupting other construction activities on-site. The Ozone project team confirmed smooth coordination and professional execution.
Project Details
- Client
- Ozone Group
- Sector
- HVAC/MEP
- Location
- Patna, Bihar
- Duration
- 1 day
Equipment Used
- Hydraulic Crane
- Chain Pulley Block
- Rollers