Industrial

Chiller Unloading & Shifting — Coca-Cola Plant, Khurda

Unloading and shifting of chiller machines at Coca-Cola's manufacturing plant in Khurda, Odisha.

Coca-Cola
Khurda, Odisha
Completed in 2 days
Chiller Unloading & Shifting — Coca-Cola Plant, Khurda
Coca-Cola manufacturing facility
Zero disruption to bottling operations
Weight-restricted plant roads managed
Positioned to exact plant specifications

The Challenge

The Coca-Cola plant required the new chillers to be unloaded and positioned within their production facility without disrupting the bottling line operations. The plant's internal roads had weight restrictions for heavy vehicles.

Our Approach

Chillers were unloaded at the plant gate using a mobile crane and transferred onto low-profile trolleys for transport to the installation point. Final positioning was done using hydraulic jacks and rollers within the plant room.

The Result

Chillers delivered and positioned as per Coca-Cola's plant layout specifications. Bottling line operations continued without interruption throughout the installation.

Project Details

Client
Coca-Cola
Sector
Industrial
Location
Khurda, Odisha
Duration
2 days

Equipment Used

  • Hydraulic Crane
  • Rollers
  • Slings
  • Chain Pulley Block

Similar Project?

Get a Quote for Your Site

Request a QuoteTalk to Our Team

Project Photos

Chiller Unloading & Shifting — Coca-Cola Plant, Khurda — Photo 1
Chiller Unloading & Shifting — Coca-Cola Plant, Khurda — Photo 2
Chiller Unloading & Shifting — Coca-Cola Plant, Khurda — Photo 3