Power & Electrical

50 MVA Transformer Unloading — L&T Jharkhand

Unloading and positioning of a 50 MVA power transformer at a new sub-station facility in Jharkhand, executed under L&T's project management.

Larsen & Toubro
Jharkhand
Completed in 1 day
50 MVA Transformer Unloading — L&T Jharkhand
50 MVA transformer — single-shift placement
Rural site with limited access managed
Ground reinforcement for crane stability
On-schedule delivery for L&T

The Challenge

The sub-station site in rural Jharkhand had limited access roads and soft ground conditions. The 50 MVA transformer had to be unloaded from a trailer with minimal crane footprint due to restricted space.

Our Approach

Ground reinforcement was carried out at the crane outrigger positions. A 100T hydraulic crane was positioned to maximise lift reach while maintaining safe load margins. The transformer was lifted, rotated, and placed directly onto the prepared foundation in a single lift sequence.

The Result

Transformer successfully placed on foundation in a single shift. L&T's project timeline was maintained with no delays caused by the handling operation.

Project Details

Client
Larsen & Toubro
Sector
Power & Electrical
Location
Jharkhand
Duration
1 day

Equipment Used

  • Hydraulic Crane 100T
  • Hydraulic Jacks
  • Rollers

Similar Project?

Get a Quote for Your Site

Request a QuoteTalk to Our Team

Project Photos

50 MVA Transformer Unloading — L&T Jharkhand — Photo 1
50 MVA Transformer Unloading — L&T Jharkhand — Photo 2
50 MVA Transformer Unloading — L&T Jharkhand — Photo 3